Biomass Project Spotlight




   
January 20, 2004
Drilling well #28.







<<   scroll over thumbnails
Rick Pennington, Project Manager for the Earth Energy project, and Ken Johnson, Fox Contractors Field Engineer.
Pipe lowered into the well.
     



February 3, 2004
Drilling well #45.







<<   scroll over thumbnails
Capped well #45 and #41.
Clean-up continues.
     



   
February 24, 2004
Well #32 with a well-head.







<<   scroll over thumbnails
Trenching in the header pipe.
Fusing the pipe that will carry the methane gas.
     
     
April 20, 2004
Preparing the pad for the flare.







<<   scroll over thumbnails
RP&L employees making preparation for transmission for Green Power - Jeff Allen, Brian Alexander and Steve Glover.
   
     
     
May 14, 2004
Final preparation before we light the flare. The flare will be used until the generation building is complete.







<<   scroll over thumbnails
Close up view of the flare to be used to monitor the quantity and quality of the methane gas.